Software effort estimates is an important part of software development work and provides essential input to project feasibility analyses, bidding, budgeting and planning. Analogy-based estimates models emerge as a promising approach, with comparable accuracy to arithmetic methods, and it is potentially easier to understand and apply. Studies show all the models are sensitive to the quality and availability data, thus requiring a systematic data treatment. In this paper, it is proposed a data pre-processing method for use in software effort estimate. The results of it on applying on applying Case Based Reasoning - CBR that enables us to enhance the precision of the estimates.

effort estimates; cost management; accuracy of estimation; ISBSG


Resumo

Estimativa de software é uma importante parte do trabalho de gerenciamento de software, fornecendo informações essenciais para projetar, analisar a viabilidade, licitação, orçamento e planejamento. Estimativas baseadas em analogia surgem como uma abordagem promissora, sendo comparável a precisão de métodos matemáticos e ainda é mais fácil de entender e de aplicar. Estudos mostram que todos os modelos são sensíveis a qualidade e disponibilidade de dados, exigindo para isso um tratamento sistemático. Este artigo propõe um método de pré-processamento de dados para utilização dos mesmos em estimativas de esforço de software. Os resultados obtidos sobre a aplicação de Raciocinio Baseado em Casos - RBC, permitiram aumentar a precisão das estimativas realizadas.

estimativas de esforço; gerenciamento de custo; precisão das estimativas; ISBSG


Universidade Federal de Viçosa – UFV- CRP

Rio Paranaíba, Brasil

{

and

Universidade Federal de Uberlândia – UFU

Monte Carmelo, Brasil

and

Instituto Nacional de Pesquisas Espaciais - INPE

Brasil

(19) reveals worrying data, 59% to 76% of the projects are delivered with an effort superior than. And 35% to 80% are delivered in delayed term. In Brazil the cenary is a little different, according to the research made by the Science and Technology Cabinet – STC, only 45,7% perform estimates for software effort(12). There are no specific studies that identify the causes of the low index of effort estimates use, but the low levels of trust in the models can be a possible cause. Despite of extensive researches, the software community is still challenged when it comes to effective estimates. As results of these researches several different models have been suggest, which include: regression analysis (15), COCOMO (7), Analysis Point per Function (3), estimation by analogies (16), clustering techniques (20) and artificial neural nets – ANN [8, 14]. The results of a research using case based reasoning (4), about the data group COCOMO (6) point out that a preliminary analysis of the historical data increases the trust of the estimates. Although the data analysis has been performed, it was not established a systematic procedure, that other researchers can apply to the generation of their models. Considering what is exposed, it is necessary to have a systematic approach that can be applied for the performing of estimates with a higher level of precision. The goal of this study is to present a method data to support the data pre-processing for software effort estimation. It was performed a case study using reasoning based on cases, about the data group ISBSG (International Software Benchmarking Standards Group) 10th version (9) based on the group of variables selected with the application of the method data presented. The article is organized in six sections. In the next section presents a brief description of the work related to the application of different approaches for software estimates, followed by a description of the CBR technique. The method the pre-processing data are then presented. Later it will be presented a case study. The last section presents our final remarks. 2 Related Study Techniques of data mining have been frequently used to exploratory data analysis in software engineering, as observed in the International Workshop about Software Repositories Mining. Several methods for exploratory data analysis have shown efficiency to the estimates executed, among them the probabilistic models used by Sentas and others 15), the Ordinal Regression method – OR, clustering applied in order to perform software quality estimates 20). In this study, it is applied ANOVA to verify the impact of the independent categorical variable over the dependent variable. This method adjusts itself to situations in which the data group presents a large number of categorical variables. Over the thirty years it was already suggested that the analogy formed a good base of forecasting the software effort 7). Therefore a tendency has been established when referring to the application of CBR to solve problems related to management of software projects. The development of a system, based on CBR, similar to a software specialist and with accuracy bigger than the model for estimates COCOMO 7) or points per function 3), was proposed by Vicinanza (18). This system was named Estor. However, as it was conceived it is necessary the acknowledge of a specialist so as to derive rules of estimates and create a Case Base. Another project based on CBR to perform estimates it is the FACE (Finding Analogies for Cost Estimating) 6). Studies show that CBR presents advantages when compared to other management techniques of knowledge and paradigm of Artificial Intelligence (1). Therefore the use of CBR brings reductions to the problems associated to specifying and codification of knowledge, manipulation of cases that failed and makes it easier for the users to identify situations apts to a high risk. Another factor that overcome the sympathy of the users is the fact that the CBR is similar to the way a human solves the problems. 3 Case Based Reasoning - CBR CBR is a technique, based in analogy, that will solve new problem getting answers from previous problems. In the reasoning by analogy it is searched the identification of similar characteristics in earlier and current problems, with the goal of evaluating answers to develop a better solution to the new problem. Considering that the quality of a CBR system which is strongly related to its experience, in other words, it depends on the number on relevant cases that composes a data base. According to Aamodt and Plaza 1), the knowledge referred to previous experiences (cases) is used to solve new problems, considering what a solution is found through the recovering of a similar case in the past. The cases are described as a group of characteristics, attributes, such as the size of a file, the number of interfaces or development method. CBR solves the new case via the recovery and adaptation of earlier cases (solved previously). The CBR process is described by Aamodt and Plaza 1) and consists of four steps: codification, recovery, reuse and retention. These four items constitute a cyclic process. So that, whenever a new problem is presented, it is decoded in a vector of attributes (or descriptions of the problem) and effects the search in the repository’s memory, the bigger the degree of attributes overlapping, the more effective will be the similarity measurements and the case recovery. The goal is to make a decreasing classification of similarity to the new case and to use solutions known of the closer k cases. Therefore, the solutions derived from the recovered cases can be adapted to be better adjust to a new case using rules, a human specialist or simply a statistic procedure. For this last case, the system is called Nearest Neighbor Technique (K - Nearest Neighbor – NN). When this new case is completed it is incorporated to the cases base. Therefore, the cases base grows with time and with the new knowledge acquired. It is of extremely importance a maintenance of the cases base, because the bigger it is the better will be. It is relevance to the reuse of new cases. 4 A Method Data Proposed When an enterprise participates in a contract bidding or even develops a software in the own organization, make effort estimation is a critical activity. The problem considered in this article is the development of a method data that can help some projects manager to predict the quantity of effort used to development of a new software. If an enterprise already has a group of items collected in its historic database, it can be used to predict a new software effort estimate and whether it does not it should create a measurement program to collect and store a historic data of its projects. Thus, before collecting data about the parameters to an estimate model it must be carefully defined what factors influence the effort of projects in a determined organization. Besides that, it is important to have an idea of how the parameters must be used to produce effective estimates. The method data presented in the First Figure is constituted of three steps: the data preparation, the pre-processing of data and the making of effort estimates.

(13), imputation techniques (17) and technique of lost data tolerance(2). 2. Normalization of numerical variables: when applying a statistics technique, it is common to verify whether the numerical variables is close to a normal curve. There are different ways to decide if a group of values have normal distribution: a) the formal tests of normality (21); b) simple visual methods such as normal probability graphic. When a variable stabilization is required, a natural transformation, in other words, log in the e base, is effective; for more information about transformations see Hoaglin et al. 9). Thus, when a non-normality occurs in numerical variables it is suggested a logarithm transformation. 3. Division of the group of data in subgroups of test and training: it has been done the same procedure as in (11) with the goal of investigating the precision of an estimation built in this study. Kitchenham developed a simple procedure to investigate the precision of the predictions done by his model over the COCOMO database. Based in this process, it was omitted a subgroup of projects (the group of test data), after that it was developed a model with the remaining projects (the group of training data) and finally it was evaluated the precision of the predictions of a model over the test data group. Thereby, it was created six pairs of training and test groups. The training group was built to remove every sixth project, beginning from the first project. Each removed data group represents the respective test data group. The second step of the method data refers to the pre-processing of a treated data group. The pre-processing must be done to identify a subgroup of variables that have a bigger significance over the effort. Previous researches developed by authors 4) and (5), show that the data pre-processing have a very significant impact in the precision on estimate models of data effort. The approach of pre-processing used, adapted from Kitchenham 11), is constituted of the following steps: 1. If necessary, to transform the variable corresponding to the effort to enhance a normality, in particular, the variance stability. Logarithms transformations are, generally, effective. To obtain more information about logarithms transformations consult 4) or 17). 2. Apply simple variance analysis (ANOVA) using each factor (to variables of nominal or ordinal scales), and simple regression analysis to each variable of absolute scale. 1. Identify the most significant factor, in other words, from a group of factors that have a statistically significant effect over the effort, chose the one that has the smallest mistake term. 2. Remove the effect of the most significant factor (in other words, for each level of the factor, it should be reduced the medium factor value from the project effort value) and obtained the residues. 3. Apply ANOVA using each remaining factor over the residues. It should be reduced the levels-of-freedom applied to a mistake term (because K-1’s levels-of-freedom were used to remove the impact of the most significant effort, in which K is the number of levels of the most significant factor). 4. Eliminate the redundant factors. The factors that were considered significant in an original analysis, but did not have a significant effect over the residues,they are confused with the most significant factor of previous analysis. Confused factors must be identified and excluded from a subsequent analysis. Although there is the risk of a factor being removed without need, it is important to recognize that over the use of this procedure it can be obtained an acceptable model. It reduces the risk of occuring certain analysis problems and it could be the base for some future researches, but as any other analysis technique, it cannot guarantee the generation of a real model. 5. Identify the next most significant effort. Only the factors that have a significant effort based on variance analysis over the residues must be considered, and again, if there are lots of candidate factors, chose the one that has the smallest mistake term. 6. Remove the most significant factor effect and obtain the second residue. 7. Repeat the analysis procedure until all the significant factors are removed, or until there is not enough levels-of-freedom to continue. It must be assured that there are at least four levels-of-freedom available for a mistake term rather than ten. Factors of the absolute and interval type can be easily included in the analysis procedure. Their impact over the variable answer can be evaluated using linear regression and calculating the medium square due to the regression equation. If a factor of an absolute or interval type is considered as the most significant, its effect should be removed and the residues analysis should continue. In this case, the levels-of-freedom attributed to the mistake term in the subsequent analysis must be reduced to one. It is important to note that in statistic, the variable and factor terms are used indistinctly. The third step it is the application and it refers to the making of the software effort estimate using a technique to be chosen according to the abilities and knowledge of the team responsible for the estimates, for example: Case Based Reasoning – CBR, Artificial Neural Nets – ANN, statistics techniques, among others. 5 Case Study In this section it is presented the data group used in this analysis, the preparation and approach techniques followed to construct and evaluate cases. To make this study it was used the ISBSG database, tenth version 9), and it was applied in it the method data described in the first Figure, which consists of a pre-processing of the stored data in this repertory and afterward evaluation of the variables that influence the case. 5.1 The Data Group The data group used was the ISBSG (International Software Benchmarking Standards Group), 10th version, 9), that consists of a total of more than 4100 projects, originated from the enterprises located in 24 different countries. Due to the fact of being a data group containing projects implemented less than 9 years ago and using software development with modern techniques, it is widely used by the academic community for the making of several researches in the software estimate area ((8)) and others). 5.2 Data Preparation In this subsection it is described a sequence of preparation of the original data group. 5.2.1 Variables Selection The initial process of variables selection it is based on literature studies about variables that influence the effort 5). It was selected 14 independent variables (Table 1) and the dependent variable: (Summary Work Effort). Table 1: Independent Variables

Table 2. Table 2: Independent Variables

second Figure shows the effect of producing a graphic representation of normal probability to the values of gross effort of the second group of data training. The diagram of data scattering is clearly not linear. Thereby, it is reasonable to assume that the data do not have a normal distribution. To enhance the normality it was applied a normal transformation, in other words, log in the e basis. The third figure shows the diagram of normal probability after the application of a logarithm transformation over the effort values of the second training group.

11)) was applied over six learning data group derived from the ISBSG data group. This section explains the approach followed the selection of these variables which will be used after in the application of CBR in the pre-processed group. 5.3.1 Variables selection The problem in the estimate using a data group with a big number of categorical variables (factors) can be solved using a procedure based in combined statistics techniques how it was described in the fourth section. The variables selected in each one of the training groups were used to make estimates over the pre-processed data group. The variables selected in each training subgroup were: TAM, LINGPROG, and PLATFDES. 5.3.2 Make Effort Estimates To make a software effort estimates it was chosen the CBR technique in the recovery of similar cases, using the K-NN similarity algorithm (K – Nearest Neighbors). To do so, it was used the WEKA software. For each test subgroup it was searched the similar cases within the database of the training group, providing then the estimate effort for each test project. 5.3.3 Precision Analysis and Estimates Evaluation Different mistake measurements have been used by different researchers, but for this study it was used two measurements of the precision of the model: the Mean Magnitude of Relative Error (MMRE) (2) and the PRED (x) (2). MMRE is the medium of the absolute percentage errors:

act is the real effort observed and Mest is the estimated effort. The Pred(x), on the other hand, is an indicator of accuracy that shows the percentage of measurements which the MRE is smaller than x. According to the definition of McConnell (22) to evaluate if an organization has done good estimates it has to commit mistakes up to 25% in 75% of the cases, in other words, PRED (25%) ≥75%.

Acknowledgements

References

References

  • (1) Aamodt, A.; Plaza, E.: (1995) Case based reasoning: foundational issues, methodological variations, and systems approaches. AI Communications, 7, p.39–59.
  • (2) Aggarwal, C.C. and Parthasarathy, S., (2001), “Mining massively incomplete data sets by conceptual reconstruction”, Proceeding of the Seventh ACM SIGKDD Conference on Knowledge Discovery and Data Mining, pp. 227-232.
  • (3) Albrecht, A. (1979) “Measuring application development productivity,” Proc. IBM Application Development Symposium, pp. 83-92.
  • (4) Barcelos Tronto, I. F., Silva, J.D.S., Sant’Anna, N., (2006). “Melhorando as estimativas de esforço de software através de um modelo baseado em analogia”. In: SEMISH- Seminário Integrado de Software e Hardware, Campo Grande, Julho, 2006.
  • (5) Barcelos Tronto, I. F., Simões da Silva, J.D. and Sant’Anna, N. (2008). “Na investigation of artificial neural neworks based prediction systems in software Project management,” Journal of Systems and Software 81(3): 356 -367.
  • (6) Bisio, R., Malabocchia, F., “Cost estimation of software projects through case base reasoning”. 1st Intl. Conf. on Case-Based Reasoning Research & Development, Springer-Velag, pp. 11-22.
  • (7) Boehm, B.W. (1981) “Software engineering economics”, Prentice-Hall, Englewood Cliffs, NJ.
  • (8) Buglione, L. Gencel, C. (2008) "Impact of Base Functional Component Types on Software Functional Size based Effort Estimation," Proceedings of PROFES 2008 Conference, LNCS 5089, A.Jedlitschka & O.Salo (Eds.), pp.75-89.
  • (9) Hoaglin, D.; Mosteller, F.; Tukey, J. “Understanding robust and exploratory data analysis”. New York: John Wiley & Sons, 1983.
  • (10) ISBSG, “International Software Benchmarking Standards Group Dataset. Release 10,” 2007, [Online]. In: http://www.isbsg.org/.
  • (12) MST Ministério da Ciência e Tecnologia, (2001) “Qualidade e Produtividade no setor de software,” In: http://www.mct.gov.br/Temas/info/Dsi/Quali2001/2001Tab402001Tab40.htm, Tabela 40 – Práticas de Engenharia de Software no Desenv. e Manutenção de Software.
  • (13) Roth, P., Missing (1994) Data: A Conceptual Review for Applied Psychologists. Personnel Psychology, v.47, pp. 537-560.
  • (17) Troyanskaya, O., Cantor, M., Sherlock, G., (2001) “Missing Value estimation Methods for DNA Microarrays”. Bioinformatics, v. 17, pp. 520-525.
  • (18) Vicinanza, S., Prietula, M.J. and Mukhopadhyay, T. (1990). “Case-based reasoning in software effort estimantion”, In Proc. 11 Int. Conf. Info. Syst., pp 149-158.
  • (19) Yang, DA. Et al (2008) “A Survey on Software Cost Estimation in the Chinese Software Industry”. Of: ESEM ’08: Procedings of the Second ACM-IEEE Intenational Symposium on Empirical Software Engineering an Measurement, pp.253-262.
  • (20) Zhong, S.; Khoshgoftaar, T.M.; Seliya, N.: (2004) “Analysing Software Measurement Data with Clustering Techniques”. IEEE Intelligent Systems, pp.20-27.
  • (21) Shapiro, S.; Wilk, M. (1965) “An Analysis of variance test for non-normality (complete samples). Biometrics”, v. 52., p.591-611.
  • (22) Mcconnell, S. (2006). “Software Estimation”, Demystifying the Black Art. Microsoft Press.

Publication Dates

  • Publication in this collection
    22 Oct 2015
  • Date of issue
location_on
Centro Latinoamericano de Estudios en Informática J. Herrera y Reissig 565 - CP 11300., Montevideo - Uruguay., Tel: (598) 2711 4244 int. 124 - E-mail: cleiejeditor@fing.edu.uy
rss_feed Acompanhe os números deste periódico no seu leitor de RSS
Ir para o topo